Build A Better Methodology

6 min read

How much more work can your team take?

Every new engagement starts with your yes

You run a transformation firm, and you decide which work it takes on. You hold the whole pipeline in your head: what is running, who is on it, and roughly when each piece will finish.

Your pipeline never arrives evenly. Some months nothing lands. Then two proposals come back in the same week, and a large tender closes on Friday.

You decide on new work by feel

So you have to answer a plain question. Can your team take this on?

You answer it by feel. You look at the calendar, you think about who is stretched, and you say yes or no. You know how many weeks your last engagement ran. You rarely know how many days of work each phase took, whose days they were, or whether the team is getting quicker at any of it.

A wrong guess costs you either way

Say yes when the team is full, and quality slips. The review happens at night, a junior's analysis goes out with a mistake in it, and you are the one who catches it, or the client is.

Say no when the team had room, and the work goes to a bigger firm.

The same gap shows up in your proposals. Your fee rests on a guess about effort, and so does your margin. When you try a new way of running a phase, you cannot tell whether it saved anything. And when one consultant looks fast, you cannot see whether the speed held up or came back a week later as rework.

Your team works hard. Without a baseline, nobody can say how much work that hard work can carry.

The quicker engagement had another story

Take a made-up change management firm, and every number in its story is made up too. Its methodology, The Adoption Path, helps a client's people take up a new system. It has five results to reach: know who the change touches, win the sponsor's backing, know how ready each group is, get people working the new way, and leave the change in the client's hands. Three of them end at a senior's check.

The firm ran it twice in a year. The second engagement finished three weeks sooner, and the founder put it down to a better team. She was about to promise the next client a shorter program.

Then she counted days of work, phase by phase, everyone's days added up.

Result

Last time

This time

Its check

Passed first time, both times

Know who the change touches

8

8

None


Win the sponsor's backing

6

7

None


Know how ready each group is

16

11

Is any group too far behind to go live?

No, sent back this time

Get people working the new way

50

40

Has use held for a full cycle?

Yes

Leave the change in the client's hands

20

16

Can the client's staff fix issues without us?

Yes

All five

100

82



Most of the three weeks came from the client moving its go-live date. Readiness looked quickest, and it had skipped the calls with each group's manager, so the ratings came back at the check. The real gain sat in training and handover, where champions inside each team had carried the change. Those two phases passed their checks first time on both engagements, and they were the ones she could count.

Count the speed that held

Delivery benchmarking means setting each engagement against your own last one, phase by phase. You need three numbers and one rule.

A baseline. For your last finished engagement, write the days of work each phase took, everyone's days added up: yours, your team's, your associates' and your subcontractors'. Weeks on the calendar are a different number, so keep them in their own column.

This time. Do the same for the engagement you are running now, or the one after.

The rule. A phase counts toward pace only when a senior checked it at its end and it passed first time, on both engagements. Speed that came back as rework is left out.

Pace. Add up last time's days for the phases that count. Add up this time's days for the same phases. Divide the first by the second. In the made-up example, the two counted phases took 70 days last time and 56 this time, so pace is 1.25 times last time's speed.

Capacity. Take the delivery hours your team has in a year. Divide by the hours one engagement took last time, then multiply by your pace. In the example, four people with 1,200 delivery hours each have 4,800 hours. One engagement took 100 days at 8 hours, so 800 hours. That is six engagements a year at last time's speed, and seven at a pace of 1.25. The sum applies the pace of the counted phases to the whole engagement, so treat capacity as an estimate until more of your phases count.

You answer from your own numbers

With a baseline, "can we take it?" has an answer you can show your team. You know how many engagements the year can carry, and how close you are to that number.

Your proposals estimate effort from what each phase took. When you change how a phase runs, the next engagement tells you whether it helped. And a consultant's speed only counts once the work has passed its check, so nobody gains by rushing.

You can test it on two engagements

You do not have to take this on trust. Take your last two finished engagements of the same methodology. Rebuild their days of work, phase by phase, from timesheets, calendars and invoices. Mark the phases that passed their check first time on both.

If the counted phases tell the same story as your gut, you have a number to plan with. If they tell a different story, you have found where your team's time goes.

The first pass takes an afternoon. The next engagement takes minutes, if your team logs hours by phase from day one.

You know what one more engagement costs

With pace and capacity in hand, you say yes to work your team can carry and no to work it cannot. You price from effort you have measured. You see which phases are getting quicker without losing quality, and which ones only look quick.

Your team stops being stretched by guesses. You stop finding out at night.

Set your next engagement against your last

The Delivery Benchmark Worksheet takes you through it. It covers when a benchmark is worth doing, its parts, a blank worksheet, ten timed steps, a full worked example, ten checks and the common mistakes. Bring two finished engagements of the same methodology, with their timesheets, calendars or invoices.

It is complimentary. We email you the link.

Ask for the Benchmark Worksheet

Enter your name and email below, and the Delivery Benchmark Worksheet arrives in your inbox. The Build A Better Baseline Practitioner Masterclass goes deeper on this article and the Benchmark Worksheet. Bring one finished engagement and its records, set out your baseline with two other founders and find the days you left out.

Where this comes from

The rule that speed counts only where quality held comes from research on knowledge work and delivery. Peter Drucker argued that the productivity of knowledge work has to be judged on its quality as well as its quantity. Donald Harter, M. S. Krishnan and Sandra Slaughter studied software products in one large firm and found that raising quality also cut cycle time and effort. Benchmarking against your own last engagement keeps the comparison fair: the same methodology, the same team and the same kind of client.

Sources

  • Drucker, P. F. (1999). Knowledge-Worker Productivity: The Biggest Challenge. California Management Review 41(2), pages 79 to 94.

  • Harter, D. E., Krishnan, M. S. and Slaughter, S. A. (2000). Effects of Process Maturity on Quality, Cycle Time, and Effort in Software Product Development. Management Science 46(4), pages 451 to 466.

Try it yourself

Delivery Benchmark Worksheet

Set one engagement against your last, phase by phase, and work out your team's pace and how many engagements its year can carry.

We email you the link.

We use your email only for what you asked for. Our privacy policy says how we handle it.

Updates

Get new articles by email

We email you when a new article is published. Nothing else.

Unsubscribe any time.

We use your email only for what you asked for. Our privacy policy says how we handle it.

Practitioner Masterclasses

Build A Better Methodology

Fourteen Practitioner Masterclasses for founders of transformation firms. Each is 60 minutes online and complimentary, and you leave with something your team can use.